Plan Review Target Time Frames

These review times represent staff’s target reviews and not the established maximum review times. To find out more information regarding our established maximum review time frames as required by SB 1598, please see the City of Goodyear Administrative Manual.

All days below are counted in business days.

Application Type/Subtype Prescreen (Administrative Review) Department Review
1st Review 2+ Review
Planning & Zoning Applications
 Projects involving Public Hearings or City Council Approval

Rezone / Planned Area Development 5 30 20

General Plan Amendments 5 30 20

Annexations 5 30 20

Use Permit / Special Use Permit 5 30 20

Development Agreement 5 30 20

Comprehensive Sign Package (requiring Council Approval) 5 30 20

Appeal 5 30 20

Variance 5 30 20
 Projects NOT involving Public Hearings

Site Plans 5 25 15

Preliminary Plats 5 25 15

Design Guidelines 5 25 15

Commercial/Industrial Design Review 5 25 15

Comprehensive Sign Package 5 25 15

Residential Design Review 5 15 10

Model Home Complex 5 15 10

Zoning Permit - All Types 5 5 5

Zoning Verification Letter 5 5 NA

Civil Applications
 Civil Application

Improvement Plans 5 25 15

Civil Plan Amendment 5 5 5

Mass Grading 5 15 5

Dry Utility / Miscellaneous Dry 5 5 3

Traffic Control Permit (TCP) 5 5 3
 Land Management and Floodplain

Final Plats 5 15 10

Minor Land Division (MLD) 5 15 10

Map of Dedication (MOD) 5 15 10

Abandonment 5 25 15

CLOMR/LOMR 5 25 15

Building Applications
 Commercial Construction

New Commercial 5 25 15

Tenant Improvement 5 15 10

Change of Occupancy 5 15 10

Demolition 5 15 10

Electrical 5 15 10

Mechanical 5 15 10

Photovoltaic 5 15 10

Plumbing 5 15 10

Swimming Pool/Spa-Custom 5 15 10

Wall or Fence 5 15 10

Revision or Deferral 5 6 6
 Fire Protection Systems

Fire Alarm 5 15 10

Fire Pump 5 15 10

Fire Sprinkler 5 15 10

Hood Suppression 5 15 10

Radio Dialer 5 15 10

Other Fire Protection (Not Listed Above) 5 15 10
 Industrial Construction

New Industrial 5 25 15

Tenant Improvement 5 15 10

Change of Occupancy 5 15 10

Demolition 5 15 10

Electrical 5 15 10

Mechanical 5 15 10

Photovoltaic 5 15 10

Plumbing 5 15 10

Revision or Deferral 5 6 6
 Multi-Family Construction

Amusement, Social Club, Recreation 5 15 10

Carport of Garage 5 15 10

Duplex, Tri-Plex, Four-Plex 5 15 10

5-9 Family Units 5 15 10

10 or More Units 5 15 10

Revision or Deferral 5 6 6
 Residential Construction

A/C Unit - New or Replacement 5 6 6

Addition/Alteration 5 6 6

Demolition 5 15 10

Detached Garage or Carport 5 15 10

Detached Guest House, Casita, or Accessory Building 5 15 10

Detached Patio or Pergola 5 6 6

Electrical 5 6 6

Photovoltaic 5 6 6

Plumbing 5 6 6

Single Family - Custom Home 5 15 10

Swimming Pool/Spa-Custom 5 6 6

Wall or Fence 5 15 10

Other Residential (Not listed above) 5 15 10
 Sign Permit 5 10 5
 Solar Permit with   SolarAPP+ 0 0 NA
 Standard Plan

Single Family Residence 5 15 10

Swimming Pool/Spa 5 15 10

EZ Permit Applications

A/C Replacement (Like for like only) 5 6 6

Electrical Meter Clearance 5 6 6

Electrical Panel (Like for like - 200 AMP Max) 5 6 6

Fire Verification - Fire Alarm 5 6 6

Fire Verification - Fire Sprinkler 5 6 6

Fire Verification - Panel Replacement 5 6 6

Fire Verification - Radio Dialer 5 6 6

Gas line - Stub only, up to 10' in length, under 50K BTU or less 5 6 6

Gas Meter Clearance 5 6 6

New Single Family Attached - Production Home 5 6 6

New Single Family Detached - Production Home 5 6 6

Patio Cover - Alumawood Only 5 6 6

Pergola/Ramada - Alumawood Only 5 6 6

Swimming Pool/Spa- Per Standard Plan 5 6 6

Water Softener - New 5 6 6

Water Heater Replacement 5 6 6

Water Meter - Landscape or Domestic Water Meter with Address Assigned 5 6 6

 

Updated 2/12/2026